Skip to main content

Articles tagged with: Turnarounds

Why You Should Upgrade From Oracle Primavera Risk Analysis to Safran Risk – Part 1

I’m Ian Nicholson, VP Solutions at Emerald Associates. I have been working with Oracle Primavera Risk Analysis (OPRA) since 2001 when it was Pertmaster, as Emerald was the exclusive Canadian distributor for Pertmaster until their acquisition by Primavera in 2006.

In this series of blogs, I will explain why I feel that all OPRA users should upgrade to Safran Risk Analysis (SR).

P6-Loader - Easy Moving of Pre-Turnaround Work to the Turnaround Window

On every Turnaround there are Pre-Turnaround activities that do not get done prior to the actual Turnaround and need to be moved into the Turnaround phase of the schedule.

The challenge is how to record actual hours earned in the PRE phase vs the TA phase, since a large number of these activities already have earned hours associated with them. Simply moving the activities would decrease the reporting of hours in PRE and create earned hours in TA for work that was actually done in PRE.

This can be done simply and quickly with P6-Loader.

Save 5 Minutes Every Time You Cancel an Activity in Primavera P6

Whenever we have a client that is interested in TAPS, we always get the question about how an activity is updated to reflect that it has been cancelled. So, how does TAPS cancel activities?

Cancelled work is work that you have decided not to perform. Typically the turnaround (TA) team doesn’t want to delete the activity because that would change the baseline hours. On the other hand, they also don’t want to progress the activity which would earn hours.

The Fastest Way to Cancel Activities in Primavera P6

Automate the Process of Updating Cancelled Activities in Primavera P6 with our Barcode Updating Technology

When planning a turnaround project you want to make sure you include all the tasks that will happen and even those that might happen. This is a great strategy in the planning phase because during the actual turnaround, you don't have time to add all of the “potential” activities that become necessary.

Now the dilemma becomes, how to cancel the tasks that your team doesn't need after all.

You could process the updates for cancelled activities using manual data entry, dealing with logic, manhours, and baselines, but if you handle a lot of these it becomes time consuming, tedious and frustrating. Lets face it, during a Turnaround that is just not a good idea. You might think that dissolving is good enough, but is it?

TAPS - Resource Earned Value - Saved Me More Than Once

On a previous assignment I worked on a 6 week turnaround project with 500,000 man-hours. After each shift update we needed to get Earned Value reports to management. It was hard enough completing updates within a 2 hour time period along with getting the next shift's reports out, but having to do full earned value was even harder.

Out of Sequence Activities In Your P6 Schedule During a Turnaround?

The unexpected happens during a Turnaround project - Let TAPS help

turnaround

“No battle plan survives contact with the enemy” - Helmuth von Moltke

When you are a scheduler on a Turnaround project you cannot expect everything to go as planned. Often at the end of your shift, when entering progress, you’ll find out something unexpected has happened in the schedule. For example, activities have been marked as completed while their predecessors are not yet started.

Why I No Longer Dread Morning Management Meetings on a Turnaround Project

How to Quickly and Effectively Develop S-Curves With Primavera P6 Project Data

I was working on TA project and was asked to provide S-Curve (Units and Cost) reporting for every morning management meeting. The client wanted to observe project trends from a schedule and cost perspective for each unit, piece of equipment and also for various contractors.

Having Trouble Changing Crew Sizes and Rates in Primavera P6?

How the P6-Loader Makes Life Easy When Working With P6 Resource Assignments and Resource Dictionaries

Working with P6 resource assignments and resource dictionaries can be extremely time-consuming. The task becomes especially tedious when it comes to planning a turnaround project with multiple daily shifts and varying crew sizes on day and night shifts, or a capital project where you have rotating work shifts with crews overlapping on the back shift.

Fix Your Primavera P6 Project Settings In Minutes

Adjusting Primavera P6 Settings and Structures with the P6-Loader

We recently had a support call from a client that started having performance issues with their P6 database during the pre-work phase of their turnaround. We looked at the Oracle 11.2.0.4 enterprise database and found a massive amount of archive logs being chewed up. In fact, it was on a scale of 1-2 GB of logs within 2-5 minutes on average. With that kind of volume it would not take long for a server to receive the dreaded Oracle error message ORA-00257: archiver error. When this happens the database usually needs more space on the device where the archive log files are stored, which results in the database not allowing any more transactions until the issue is corrected.

Primavera P6 What-If Analysis, Resourcing and Turnarounds

A turnaround is a very large undertaking. The first and foremost priority must be safety. Always keeping that in mind, the team must address all aspects of the in scope (known work) as well as found work (which has the potential for a few surprises!). Scheduling of such an event is a must!