Monitoring Large P6 Groups with P6-Auditor

P6-Auditor helps find users who made mistakes in P6

Monitoring Large P6 Groups with P6-Auditor

Deleting and editing global data happens; P6-Auditor can help

Written by Nicole Jardin

Client Overview

Large Electrical Utility with several P6 databases with internal and external scheduling teams needed a way to manage and report on functions inside P6.

Challenges

  • With a large team of P6 users, it is hard to track down when projects are deleted

  • Ensuring that the EPS does not get changed when users are cutting and pasting projects was a challenge

  • When managing a resource pool of over 10 thousands crews, making sure your resource dictionary is maintained and coding kept up to date with more than one admin can be error prone

Results

  • Tracing project deletes easily and rollbacks if required

  • Reporting on update frequencies - actual starts, actual finishes, and percent completes

  • Edits to the resource dictionary that were not expected including deletes and cut and pastes

  • Verifying changes to activity codes and who made them as well as when they were made

  • Tracing EPS moves that no user admitted to

  • Finding logic changes that should not have been made as well as task deletes

PIMS -> P6 Integration

Integration between PIMS and Primavera P6 ensures quality compliance reporting for large electrical company.

PIMS -> P6 Integration

compliance reporting made easy

Written by Nicole Jardin

Client Overview

Supplying Electricity to clients throughout Alberta requires strong program management. Ensuring that all regulatory reporting is complied with in multiple jurisdictions with differing rules and requirements can be a challenge.

Challenges

  • Ensuring regulatory reporting compliance was up-to-date and accurate on a daily basis let alone for monthly reporting

  • Managing changing conditions was difficult to ensure all stage gate reporting reflected these changes

Results

  • Integrated to PIMS key milestones for stage gates

  • Ensured consistent reporting - and reduced errors significantly

  • Automatic integration on project creation with templates with estimate dates

  • Within 4 weeks system was running

  • Cloud and on-premise integration