Skip to main content

CAPPS Makes Updating Hundreds of Projects Easy

Remote PMs get updates in on time with CAPPS

CAPPS Makes Updating Hundreds of Projects Easy

Remote Project Managers get updates in on time

Written by Nicole Jardin

Client Overview

When managing a multi-million, country-wide building upgrade and retrofit program with over 150 project managers, getting timely updates is very challenging.

Challenges

  • Getting bi-weekly status updates from 150 remote project managers was taking over a week to accomplish

  • Capturing monthly costs in a timely manner to get the program reporting reviewed and validated without major overtime for the project controls team

  • Ensuring consistent updating of key milestones and schedule slippage analysis

  • Getting all PMs to take responsibility for the updates and the timelines and understanding inter-project dependency impacts

Results

  • P6-Loader was used to clean up project templates for some 500 projects in play to acquire consistency

  • CAPPS is used for weekly updates by over 150 PMs

  • The project controls teams review and approve all updates in P6 and discuss any anomalies with the PMs right away

  • CAPPS is allowing meeting updates to run more efficiently with the on-screen grid

  • Program management reporting is now being done with a lot less stress and overtime

  • P6-Calculator allows for flagging of variances and easy filtering of late and overdue items for the schedulers to find across hundreds of projects

No video selected.

Related Articles

Recent Blogs

Upcoming Free Webinars

18 Dec
OPC-Integrator Webinar - New Tool Release - 2024-12-18
2024 Dec 18 10:00 am MST - 11:00 am MST