Skip to main content

Oracle Primavera P6 20.12.8.0 Released

IMPORTANT UPDATE: The major patch 20.12.8.0 for P6 EPPM is now available. The following list of issues have been fixed for Primavera. To see the other released patches and updates for P6 EPPM v20.12, please visit My Oracle Support.

WEB

33149547 INTERNAL-FP:[SQL SERVER] SELECTING A PARENT CODE VALUE ONLY LOADS RESOURCE DATA FOR IMMEDIATE CHILD CODES VALUES ON THE RESOURCE > ANALYSIS PAGE GROUPED BY RESOURCE CODE

33146020 VIEW SERVICE STATUS IMPORT JOB PROJECTS COLUMN SHOWING IMPORTING EPS NAME RATHER THAN THE IMPORTED PROJECTS NAME.

33141555 RESOURCE ASSIGNMENTS VIEW DOES NOT LOAD

33123131 FP - [SQL SERVER] RESOURCE > ASSIGNMENTS PAGE INCORRECT EXECUTES SECOND TASKRSRC STATEMENT WHEN FIRST STATEMENT MATCHES OR EXCEEDS DATA LIMIT AND VIEW CONTAINS UDF OR CODE

33085632 ERROR INVALID PATH WAS REQUEST WAS RECEIVED WHEN TRYIN TO LOGIN IN P6 WEB

33036441 GLOBAL CALENDARS ARE NOT SORTING PROPERLY IN ENTERPRISE DATA

33164010 FP - P6 RESOURCEASSIGNMENT SERVICE ALWAYS RETURNS PRICEPERUNIT AS NULL VALUE FOR A ROLE

33124852 ERROR: JAVA.LANG.NUMBERFORMATEXCEPTION: NULL WHEN LOADING RELATIONSHIPS USING ACTIVITY CLASS.

32999690 EPS IS UNDER FILTER FOR PORTFOLIOS CAUSES AN ERROR

32671449 FROM P6 UN/CEFACT XML EXPORTS BLANK EARLY START, EARLY FINISH, LATE START, AND LATE FINISH DATES WHEN ACTUAL DATES EXIST FOR LOE & WBS SUMMARY TYPES

32559858 RESOURCE ANALYSIS PAGE TAKES OVER 1 MINUTE TO LOAD

33066149 CHANGE ERROR RETURNED WHEN SUMMARIZING PROJECT WITH NO CALENDAR ASSIGNED

33167149 IN P6 WEB IF A USER IS ASSIGNED A UIV THAT DOES NOT ALLOW ACTIVITY UDF EDITING THE UIV USER IS STILL ABLE TO EDIT THE UDF ON THE LOWER UDF TAB

33130147 SERVICE STATUS PAGE IN P6 IS UNABLE TO LOAD - GETTING AN ERROR

Team Member

33160145 AFTER UPGRADE TEAM MEMBER IS TAKING THREE MINUTES TO OPEN THE PAGE

CLOUDCONN

32986124 CLOUDCONNECT DOES NOT SYNCHRONIZE DATA

P6PRO

33102367 CURTAINS ATTACHMENT NOT PRINTING OVERLAP IN PDF OR PRINT PREVIEW

32818318 P6 SHOWS NOT RESPONDING FOR 8-12 MINUTES WHEN ASSIGNING BASELINES

33124349 IN P6 PRO DURING XER IMPORT IF A NON-DEFAULT IMPORT TEMPLATE IS SELECTED TO USE IT'S SELECTION IS NOT SAVED OFF.

33105897 IN P6 PROFESSIONAL 'STATUS' VALUE IS MISSING FROM THE GROUP BY PICKLIST AND DOES NOT PRE POPULATE THE 1ST GROUP BY ROW WHEN CHOSEN

33104535 P6 VISUALIZER SCHEDULE COMPARISON IS NOT WORKING

33103928 ERROR: EVENT CODE: RRAGC-0089-9 WHEN LEVELING PROJECT

32779443 CORRUPTED BASELINES CREATED INTERMITTENTLY

32617682 FROM P6 UN/CEFACT XML EXPORTS BLANK EARLY START, EARLY FINISH, LATE START, AND LATE FINISH DATES WHEN ACTUAL DATES EXIST FOR LOE & WBS SUMMARY TYPES

31704565 UNABLE TO LOCK PROJECT AT REQUESTED ACCESS LEVEL WHEN IMPORTING MSP XML FILE TO UPDATE AN EXISTING PROJECT

33202099 SCHEDULE PROJECT SLOW PERFORMANCE IN 20.12.7

32955489 XML IMPORT FAILS TO IMPORT TO SQL SERVER PPM DATABASE

33028808 WEBSERVICE FILTER LASTPUBLISHEDON
  • Last updated on .