Turnaround Planning with Outsourced Contractors

Large oil and gas company uses P6-Loader to develop turnaround plans.

Moving to consistent processes and reporting

Written by Nicole Jardin

Client Overview

Large oil plant in Australia needed a more efficient way to develop their turnaround plans. This was typically being done by an outsourced engineering and contractor joint venture every 2 years. So each time different processes and team members were working with different methodologies.

Challenges

  • Struggling to build detailed schedules since they had to pull data from internal systems and contractor inputs and remap the data into standard template formats

  • Working with contractors during the turnaround providing updates in different ways

Results

  • Streamlined data imports by over 30%

  • Drastically reduced manual data entry by 50%

  • Improved standardized reporting during the planning stage and execution

  • Expanding P6-Loader’s use into other groups to improve the usage of P6

From Our Customer

We saved 6 weeks on our planning process, and were able to get feedback more quickly after using P6-Loader.

Moving to the Primavera Cloud Made Easy

Used the P6-Loader to move a client to the Primavera Cloud in two weeks.

In 2 weeks - all projects were ready

Written by Nicole Jardin

Client Overview

Project Management specialist overseeing a large building remediation program after Hurricane Sandy needed to move from on-premise P6 program development to the Primavera Cloud to share schedule information with Contractors and Owners Representatives.

Challenges

  • Setup a new P6 environment in the Primavera Cloud within 2 weeks

  • Transfer all P6 program data for over 750 projects in a standalone PPM database

  • Over 400 baselines needed to be moved as well

Results

  • Emerald provided P6-Loader aaS

  • Enterprise Data: built and loaded for EPS, OBS, Users, User Profiles

  • Global Data: merged and cleaned up while loading over 400 Resources and 50 Calendars

  • Project Data: 756 projects, 455 Baselines, 265,802 activities. Activity codes, resource assignments, and relationships were all transferred.

  • Approach - used a combination of XER and P6-Loader functionality

  • Saved weeks of manually re-creating global data, users/profiles, and baseline management. Went live 1 week after getting files.

SAP Integrated to Primavera P6 with the P6-Loader

Large Australian rail company uses the P6-Loader to integrate SAP to Primavera P6.

Monthly cost loading made easy for hundreds of projects.

Written by Nicole Jardin

Client Overview

Large railway projects need a tremendous amount of coordination and strong scheduling. Managing monthly costs and updates from several regional contractors so that shareholders can be informed of status can be a challenge.

Challenges

  • Gathering updates from contractors working in remote regions to keep forecasting accurate

  • Ensuring costs were captured and validated against the schedule performance

Results

  • Streamlined the efforts of updating down from 4 person weeks to 2 person days. Data Imports by over 30%.

  • Errors and mismatches were reduced significantly

  • Several macros made this extract and upload much more reliable than manual inputs

  • Reloading every day during the update window was smooth

From Our Customer

SAP to P6 updates were easy to perform so that forecasting was much more accurate.

AVEVA to Primavera P6 Engineering Document Integration

We integrated Aveva with P6 to drastically reduce the time our client spent updating their capital projects

Simplifying Engineering Updates

Written by Nicole Jardin

Client Overview

One of Canada's many potash companies runs all their capital projects with Primavera P6. With one scheduler on the team, it is difficult to keep up with the dozens of projects on the go to ensure monthly reporting is accurate.

Challenges

  • Updating some 20+ projects in P6 was time consuming at the end of each month

  • Mid-month reporting was not easy to do without spending extra hours to get all the updates into P6

  • Going over the updates with the extended team took a lot of coordination to schedule with so many people with different schedules

Results

  • Integrated documents statuses from Aveva

  • Templated the different task types and package types with preset calculation methods

  • Documents planned, in progress, completed, deleted

  • Set the start dates of tasks in progress, updated the percent completes and flagged changes to the tasks

  • Updated the resources - actual labor units

Calendar Rolldown using P6-Loader

Creating EPS and OBS with P6-Loader

P6-Loader: Usage Sheets

Large Energy Company Migrates to Clean Primavera P6 Environment

The daunting task of cleaning up 10 years of projects was made easy with P6-Loader so archiving, cleaning, fixing and upgrading could happen.

P6-Loader made it easy

Written by Sue Hopkins

Client Overview

The client is a large Canadian producer, transporter and marketer of natural gas, oil and natural gas liquids. They use P6 for many project controls functions including their capital program. After years of working in a P6 database they wanted to move to a clean P6 environment.

Challenges

  • Their IT department needed assistance in Upgrading and Migrating Major Projects and Facility, Engineering and Construction databases to a new environment

  • Their Security Profiles, User and Global Data, some of which were corrupt needed to be cleaned up prior to move to new environments

  • Move large live projects with up to 100 baselines to the new environment in a short amount of time while users were not active

Results

  • Databases edited and cleaned up prior to migration including Security Profiles, User and Global Data, some of which were corrupt, using the P6-Loader tool

  • Archived old projects in place and moved over 400 projects and baselines to a new environment with only one weekend of down time

  • Migrated data was validated and compared to previous database to ensure all data was moved accurately

  • Saved hundreds of hours of manual work

Fabrication Program Management

Large Pre-Fab Manufacturer uses P6-Loader to get control over their planning, scheduling and cost controls.

competing priorities resolved

Written by Nicole Jardin

Client Overview

Calgary pre-fab manufacturer with international projects needed to get better control over the planning, scheduling and cost controls of several hundred projects on the go at once for wide ranging clients.

Challenges

  • Fabrication team was swamped and priorities were unclear

  • Change orders were impacting priorities

  • Needed a common approach to planning 250 projects on the go

Results

  • Used the P6-Loader to develop P6 Structures - EPS/OBS/Cost Accounts

  • Fully templated program

  • Cost Loading Changes with Overhead, Profit tracking

  • Daily Costing Reporting

Exactly Which Projects Are Using Each Global or EPS Activity Code?

In P6, identifying which projects are using each Activity Code in a quick, consolidated, easy to use manner is challenging. Especially when you consider some clients have a LOT of baselines.

But is this is r-e-a-l-l-y information we need to be able to capture? In my experience, there are a number of scenarios where that answer is a resounding “Yes”! One common example – the Activity Codes Dictionary needs to be cleaned up.

DOTs and Emerald Associates - We Can Make Your Job Easier

Emerald Associates is well known in the US and Canada for our homegrown add-on tools for Primavera P6. We have assisted numerous companies in many diverse areas to get the most out of their P6 software. You may wonder how our tools can assist in the Department of Transportation (DOT) field to get more done in P6 with less time while still providing useful data to your stakeholders and remaining good stewards of the public's funds. Our tools will help you do more work in less time, so that your project management group has more time to analyze and perfect their schedules.

Global Calendars – Exactly Which Projects Are Using Each Calendar?

In P6, identifying each specific project using each of the Global Calendars in a concise, fast, easy to use manner is challenging. Some may think this is not necessary very often, but in my experience, it has been quite the opposite!

Is this functionality already handled in Primavera P6, Client or Web? A very good question - let’s have a look.

P6-Loader Usage Sheets Revolutionize P6 Database Maintenance

When you have a large number of users in your P6 database, it is surprising how quickly that database can get “clogged up” with a lot of unwanted data. This happens even when using Sandbox databases, restricting privileges and every other trick you have thought of; long time P6 users know what I am talking about.

P6-Loader - Easy Moving of Pre-Turnaround Work to the Turnaround Window

On every Turnaround there are Pre-Turnaround activities that do not get done prior to the actual Turnaround and need to be moved into the Turnaround phase of the schedule.

The challenge is how to record actual hours earned in the PRE phase vs the TA phase, since a large number of these activities already have earned hours associated with them. Simply moving the activities would decrease the reporting of hours in PRE and create earned hours in TA for work that was actually done in PRE.

This can be done simply and quickly with P6-Loader.

The P6-Loader For Turnaround Projects